Start of works on stripping of construction area, located at: Krasina Str., estate 3, buildings 1, 3, 4, 6, 7

Starting from January 28, 2014 General Directorate Centre, acting as the technical customer on design and construction of a business centre with an underground parking, located at Krasina Str.,, estate 3, buildings 1, 3, 4, 6, 7, initiated demolition of building, located at Krasina Str., 1, estate 3 using the labor of the contractor company OAO UM #4. Completion of works on demolition of existing 5 constructions is planned for end of May 2014.